Design accidental loads report
A class with identifier
http://rds.posccaesar.org/ontology/plm/rdl/PCA_100006154
Source ontology | norsok-z001 |
Comment | Covering all possible loads along the pipeline route such as 3rd party activities (e.g. anchoring, trawling, construction, traffic). Could be a part of pipeline desig report. |
NORSOK Z-001 rationale | Accidential load chosen to be used as basis for design. In the design phase, the design accidental load could be more conservative (higher) than the dimensioning accidental load, but should never be lower. |
NORSOK Z-001 interests stakeholder category | pipeline engineering |
NORSOK Z-001 describes structural element | Facility |
NORSOK Z-001 definition | Covering all possible loads along the pipeline route such as 3rd party activities (e.g. anchoring, trawling, construction, traffic). Could be a part of pipeline desig report. |
skos:broadMatch | technical property information |
skos:broader | Report |