FAT procedure
A class with identifier
http://rds.posccaesar.org/ontology/plm/rdl/PCA_100006201
| Source ontology | norsok-z001 |
| Comment | A procedure describing the stepwise testing to be performed for the equipment after completed manufacturing. Test set-up and test equipment is defined |
| NORSOK Z-001 rationale | Give clear test instructions and provide information to customers concerning test standards and acceptance criteria. |
| NORSOK Z-001 interests stakeholder category | subsea engineering |
| NORSOK Z-001 describes structural element | Equipment |
| NORSOK Z-001 definition | A procedure describing the stepwise testing to be performed for the equipment after completed manufacturing. Test set-up and test equipment is defined |
| skos:broadMatch | instructive information |
| skos:broader | Procedure |