Outline precommissioning procedure
A class with identifier
http://rds.posccaesar.org/ontology/plm/rdl/PCA_100006351
Source ontology | norsok-z001 |
Comment | Input to design basis for pipeline and risers design and installation methodology. |
NORSOK Z-001 rationale | Outline procedure for the pre-commission activities and schedule. |
NORSOK Z-001 interests stakeholder category | subsea engineering |
NORSOK Z-001 describes structural element | System |
NORSOK Z-001 definition | Input to design basis for pipeline and risers design and installation methodology. |
skos:broadMatch | instructive information |
skos:broader | Procedure |