Source ontology | norsok-z001 |
Comment | The following list shows the deliverables and structure of the fabrication records for structural steel and aluminium:
- As-built Users Guide;
- Index of design drawings with reference to fabrication drawings;
- Index of material, design, fabrication, specifications and documents, used by Contractor;
- Welding procedure specifications;
- Welding procedure qualification records;
- Repair procedures and specifications;
- Weld summary index;
- Material specification system;
- Assembly procedures;
- Production test reports;
- PWHT reports;
- Repair and deviation reports;
- As-built Design Contractor originated design drawings, mark-ups;
- List of fabrication drawings containing Main Weld numbers;
- Documentation of rubber coating of j-tubes shall include the following:
- Detailed design calculations of thermal insulation requirements, and the development of the insulation aspects of the product, during its lifetime expectancy in service. These calculations shall apply for the components and field joints and take into consideration all the necessary properties including application and installation.
- Detailed information about properties of the coating and coating system qualification.
- All materials data, test certificates and product data sheets (PDS).
- Detailed coating procedure, as a minimum including the information listed in the APS.
- Detailed field jointing procedure.
- Detailed repair procedure.
- Detailed procedures for handling and storage of line-pipe.
- Detailed Quality plans / Inspection and Test Plan (ITP). All witness and hold points shall be identified.
- Test records and results.
- Inspection reports and records.
- Repair and recoating records.
- All relevant coating application variables.
- The personnel qualification record shall constitute proof that the personnel designated to carry out the work are properly qualified to do so. The following list shows the deliverables and structure of the fabrication records for Concrete structures:
|
NORSOK Z-001 interests stakeholder category | structural engineering |
NORSOK Z-001 describes structural element | Equipment |
NORSOK Z-001 definition | The following list shows the deliverables and structure of the fabrication records for structural steel and aluminium:
- As-built Users Guide;
- Index of design drawings with reference to fabrication drawings;
- Index of material, design, fabrication, specifications and documents, used by Contractor;
- Welding procedure specifications;
- Welding procedure qualification records;
- Repair procedures and specifications;
- Weld summary index;
- Material specification system;
- Assembly procedures;
- Production test reports;
- PWHT reports;
- Repair and deviation reports;
- As-built Design Contractor originated design drawings, mark-ups;
- List of fabrication drawings containing Main Weld numbers;
- Documentation of rubber coating of j-tubes shall include the following:
- Detailed design calculations of thermal insulation requirements, and the development of the insulation aspects of the product, during its lifetime expectancy in service. These calculations shall apply for the components and field joints and take into consideration all the necessary properties including application and installation.
- Detailed information about properties of the coating and coating system qualification.
- All materials data, test certificates and product data sheets (PDS).
- Detailed coating procedure, as a minimum including the information listed in the APS.
- Detailed field jointing procedure.
- Detailed repair procedure.
- Detailed procedures for handling and storage of line-pipe.
- Detailed Quality plans / Inspection and Test Plan (ITP). All witness and hold points shall be identified.
- Test records and results.
- Inspection reports and records.
- Repair and recoating records.
- All relevant coating application variables.
- The personnel qualification record shall constitute proof that the personnel designated to carry out the work are properly qualified to do so. The following list shows the deliverables and structure of the fabrication records for Concrete structures:
|
skos:broadMatch | validation and verification information |
manufacturing information | |
skos:broader | Manuals |