Manufacturing record book (MRB)
A class with identifier
http://rds.posccaesar.org/ontology/plm/rdl/PCA_100006308
MetadataThis section provides information about 'PCA_100006308' itself.
Source ontology | norsok-z001 |
Comment | MRB requirements:n - The Manufacturers standard MRB can be deliveredn - If additional documents required by Company, they should be submitted as separate ndeliverables.nnAn MRB shall include:n(depending on the equipment it describes some of the below listed documents may not be napplicable)n - Introduction and MRB indexn - List of certificatesn - Analysis, tests, calculations, curves and tables (*)n - Balancing certificatesn - Calibration certificatesn - Certificates needed for re-certification of equipmentn - Certificates of conformance (*)n - Documentation for CE markingn - Final inspection, preservation, packing and dispatchn - Final test/acceptance reports (FAT reports)n - Instrument calculations (safety and relief valves) (*)n - Lifting certificatesn - Manufacturing procedures and reportsn - Material certificates (*)n - Material testing and controln - Material traceability listn - Mechanical/structural calculations and analysesn - NDE drawings, sketches and other NDE doc.n - Non-conformance reportsn - Painting proceduren - Performance / functional test procedures and reportsn - Photos of equipment/inspectionsn - PMI reportn - Pressure test certificatesn - Telecommunication test report(s), Vendor reports, MC&C reportsn - Third party verification reportsn - Type Cert.’s/EX Certificates/Product Cert.’s. issued by third party (*)n - Weight certificates (*)n - Weld Summary Index and NDE logn - Welding proceduresn - Welding procedure qualification records (where applicable)nn(*) Documents that may be required as separate documents. See chapter 4 for equipment ntype specific requirements. |
NORSOK Z-001 rationale | MRB is a collection of necessary documents to demonstrate that the requirements with respect to design, calculation, production, testing and possible specified traceability requirements for materials and fabrication, are fulfilled.If the documentation normally contained in MRB is issued separately, a reference to such documents is sufficient in the MRB. |
NORSOK Z-001 definition | MRB requirements:n - The Manufacturers standard MRB can be deliveredn - If additional documents required by Company, they should be submitted as separate ndeliverables.nnAn MRB shall include:n(depending on the equipment it describes some of the below listed documents may not be napplicable)n - Introduction and MRB indexn - List of certificatesn - Analysis, tests, calculations, curves and tables (*)n - Balancing certificatesn - Calibration certificatesn - Certificates needed for re-certification of equipmentn - Certificates of conformance (*)n - Documentation for CE markingn - Final inspection, preservation, packing and dispatchn - Final test/acceptance reports (FAT reports)n - Instrument calculations (safety and relief valves) (*)n - Lifting certificatesn - Manufacturing procedures and reportsn - Material certificates (*)n - Material testing and controln - Material traceability listn - Mechanical/structural calculations and analysesn - NDE drawings, sketches and other NDE doc.n - Non-conformance reportsn - Painting proceduren - Performance / functional test procedures and reportsn - Photos of equipment/inspectionsn - PMI reportn - Pressure test certificatesn - Telecommunication test report(s), Vendor reports, MC&C reportsn - Third party verification reportsn - Type Cert.’s/EX Certificates/Product Cert.’s. issued by third party (*)n - Weight certificates (*)n - Weld Summary Index and NDE logn - Welding proceduresn - Welding procedure qualification records (where applicable)nn(*) Documents that may be required as separate documents. See chapter 4 for equipment ntype specific requirements. |
skos:broadMatch | validation and verification information |
skos:broader | Manuals |