PCA Reference Data and Services
Toggle Dark/Light/Auto mode Toggle Dark/Light/Auto mode Toggle Dark/Light/Auto mode

Process safety report

A class with identifier http://rds.posccaesar.org/ontology/plm/rdl/PCA_100006395

MetadataThis section provides information about 'PCA_100006395' itself.

Source ontology norsok-z001
Comment The process safety report shall be one single report for the plant (i.e. not split into several reports), and this report shall be updated whenever relevant modifications to the plant are performed.nnThe process safety report shall as a minimum include/describe:n - The philosophy for process safety functions, i.e. pressure protection, level protection, temperature protection and overflow protection;n - Process safety functions including premises for the design of the safety function:n - Documentation of how these premises are fulfilled in design and shall be maintained, so that future modifications will not compromise the design intention;n - Relief cases (all) for relief valves including the dimensioning ‘required capacity’ and the; ‘rated capacity’n - Instrumented shutdown:n - The structured review of the required instrumented shut down functions:n - Documentation of the performed structured analysis utilizing SAT, SAC and SAFEs in accordance with ISO 10418/API RP 14 C;n - Documentation of the structured review carried out to determine required instrumented shutdown functions, e.g. LOPA (if applicable); n - The philosophy for leakage detection;n - Listing of valves that need to be secured in the correct position as a part of the process safety design, including reasoning for securing the valve position and the choice of method;n - Heat conservation philosophy for safety critical heat conservation including operating and maintenance practice to ensure proper reliability of the heat conservation systems;n - Safety critical procedures (administrative control);n - Safety critical check valves;n - Pipeline protection (if relevant);n - The reasoning for the chosen sectionalisation of the process;n - The relief valve schedule;n - PSD response time.nnThe dynamic simulation model(s) used for the simulations of the Inadvertent valve opening (IVO) and Choke collapse (CC) scenarios, e.g. the Olga model, shall be delivered and shall represent the As built design of wells, flowlines and topside piping.
NORSOK Z-001 rationale In accordance with API 521 chapter 4.7, and authority regulation "Aktivitetsforskriften" §20.
NORSOK Z-001 interests stakeholder category process engineering
NORSOK Z-001 describes structural element Facility
NORSOK Z-001 definition The process safety report shall be one single report for the plant (i.e. not split into several reports), and this report shall be updated whenever relevant modifications to the plant are performed.nnThe process safety report shall as a minimum include/describe:n - The philosophy for process safety functions, i.e. pressure protection, level protection, temperature protection and overflow protection;n - Process safety functions including premises for the design of the safety function:n - Documentation of how these premises are fulfilled in design and shall be maintained, so that future modifications will not compromise the design intention;n - Relief cases (all) for relief valves including the dimensioning ‘required capacity’ and the; ‘rated capacity’n - Instrumented shutdown:n - The structured review of the required instrumented shut down functions:n - Documentation of the performed structured analysis utilizing SAT, SAC and SAFEs in accordance with ISO 10418/API RP 14 C;n - Documentation of the structured review carried out to determine required instrumented shutdown functions, e.g. LOPA (if applicable); n - The philosophy for leakage detection;n - Listing of valves that need to be secured in the correct position as a part of the process safety design, including reasoning for securing the valve position and the choice of method;n - Heat conservation philosophy for safety critical heat conservation including operating and maintenance practice to ensure proper reliability of the heat conservation systems;n - Safety critical procedures (administrative control);n - Safety critical check valves;n - Pipeline protection (if relevant);n - The reasoning for the chosen sectionalisation of the process;n - The relief valve schedule;n - PSD response time.nnThe dynamic simulation model(s) used for the simulations of the Inadvertent valve opening (IVO) and Choke collapse (CC) scenarios, e.g. the Olga model, shall be delivered and shall represent the As built design of wells, flowlines and topside piping.
skos:broadMatch explanatory technical information
instructive information
health protection information
equipment protection information
environment protection information
security information
skos:broader Report

ConstraintsThis section lists constraints that members of 'PCA_100006395' shall satisfy.

ContextThis section provides super- and subtypes as well as members of 'PCA_100006395'.